High-tech Solutions BV·Waregem, Belgiuminfo@high-techsolutions.be
Industrial engineering consultancyMaintenance · Automation · Projects

Expertise Portfolio 2006–2026

20 years leading technical teams

The electromechanical engineers of High-tech Solutions BV have led maintenance, shutdown, automation and infrastructure projects in Belgium, the Netherlands and internationally. This hands-on experience is what we use to select, test and train our candidates.

Explore
the portfolio

Choose one or more clients, a sector or a specific project: the figures, the table and the charts update instantly.

Clients

Percentages relative to the total budget of the selected projects.

Project details

Click a header to sort, or a row to open the project sheet.

Total budget and share under our responsibility

Grey: total project budget. Blue: share managed. Logarithmic scale. Hover over or click a point.

Labour hours per project and cumulative %.

Average workforce deployed per project, in FTE. Blue: above the direct supervision threshold (≈ 12 people), which requires team leaders. Light blue: short peak.

Average FTE per calendar year, dated projects only.

2016: annual average of an Imerys shutdown of about 127 FTE over one month. Short undated projects are not included.

Management
analysis

Overall reading of the complete portfolio, all clients combined.

MAINTENANCE

Permanent teams

Lotus (15 FTE), Coca-Cola (13 FTE), Lantmännen (23 FTE): direct supervision, shift planning, technician training, preventive plans. Beyond 10 to 12 people, 2 to 3 team leaders take over.

PROJECTS

Multi-site teams

Stow (59 FTE), Acotec (10 FTE), DZI (9 FTE): indirect management through 6 to 7 team leaders or subcontractors, budget monitoring and reporting.

SHUTDOWNS

Mobilisation peaks

Imerys, Gunvor, maritime projects: coordination of 13 to 16 contractor managers (24 suppliers at Imerys), safety and a tight intervention schedule.

A model consistent with reality. For Lotus, the calculation gives 15 FTE over 24 months, for an actual team of about 15 technicians. For Imerys, 127 FTE over one month, for 150 workers on site. Both cross-checks confirm the order of magnitude.

Growing responsibility. The share managed rises from 5% (Volvo, Coca-Cola) to 10–15% (Lotus, Lantmännen), then 40% (Stow) and 70 to 100% (Acotec, Imerys, Gunvor, DZI): on recent projects, a full project manager role.

A lasting presence. Over about 20 years, the portfolio represents an average of 11 FTE supervised per year, with peaks of 23 FTE (2018–2019) and 69 FTE (2021).

Management of a €25.9M portfolio across 23 industrial projects, i.e. more than 370,000 hours of technical labour.
Supervision of maintenance teams of 13 to 23 technicians and coordination of nearly 60 people on average on an 18-month international project.
Management of a technical shutdown involving 150 workers and 24 suppliers over one month, with a restart without any major incident.
Full budget responsibility (70 to 100%) on recent infrastructure, petrochemical and maritime projects.
MethodCalculation assumptions and simulator

The calculation covers the “managed portfolio” share, i.e. the budget actually placed under the project manager's responsibility.

  • Labour share: 80% of the portfolio; the rest covers equipment, material subcontracting and expenses.
  • Loaded hourly cost: €55/h for a technician in Belgium.
  • Productive hours: 1,650 h per year per FTE, i.e. 137.5 h per month.
  • Durations: actual dates for dated projects; estimated at 1 to 10 months for short projects.
Hours = Portfolio × labour share ÷ hourly cost
Average FTE = Hours ÷ (Duration in months × 137.5 h)

The sliders change every figure on the page. Even under the cautious assumption (60%, €65/h), the total stays close to 239,000 hours.

Hours by labour share and hourly cost